BUDGET TRACKER
$98K
of $120K total
82%
$2K
Burn / week
$-14840
Projected underrun
$105K
Projected final
MILESTONE PROGRESS
4 / 5
milestones complete
Data mapping & schema translation
Oct 1, 2025
Batch migration scripts (Phase 1)
Dec 1, 2025
UAT with finance team
Feb 15, 2026
Parallel-run validation
Apr 1, 2026
Cutover & legacy shutdown
May 30, 2026
ASSIGNED TEAM
No engineers assigned yet.
COMPLETION
ACTIVITY LOG
J
ManufactureMax signed off on Phase 4 data quality report. Go-ahead for cutover planning.
A
CRITICAL: Found 14K records with null foreign keys during parallel-run. Quarantined for manual review.